New Fire Station Construction 2023
On Nov. 8, 2022 the voters approved the construction of a new Fire Station on School Street.
Design Build,
Construction Management and
General Contracting.
GFC will manage the project in 2023.
Chief Vincent Pelletier was appointed by the Select Board on 12/19/2022 Overseer of Construction for the Town of Limerick of the New Fire Station project planned for 2023 on School Street.
Great Falls Construction of Gorham, ME is the general contractor.
2023 Change Orders
Request from Great Falls Construction
Great Falls Construction is pleased to be working in Limerick on the new Fire Station. You are encouraged to reach out to them if you have any questions. They ask however that you not enter the property for any reason without being properly escorted. To do so without consent is considered trespassing. It is an active construction site and unmonitored personnel can create a hazard to themselves and those around them. THANK YOU for your cooperation.
Shovel Ready!
Building Materials delivered to School Street site on 7/10/2023.
NEW FIRE STATION UPDATE 9/22/2023
Last foundation pour for the immediate future. Site work and base coat paving up next, followed by erecting steel in early October.
Foundation
9/22/2023
Foundation
9/22/2023.
UPDATE: New Fire Station's foundation completed on 10/9/2023. Rear basement floor has been completed. Steel company representatives reviewed the site on 10/10/2023 and crew will begin process for steel installation on 10/11/2023. Cranes will appear soon to start erecting framing. Water and Sewer connections have been completed at street. Location of new fire station is on School Street.
Limerick's new Fire/EMS Station starting to take shape with erection of steel framing. 10/2023
.
Steel framing continues to take shape 10/22/2023
Roof is taking Shape!
10/28/2023
Roof almost complete!
11/01/2023
Radiant Heating being installed in flooring.
11/26/2023
Bay Floor Complete
12/21/2023
New Red Doors Installed
Feb 2024.
February 16, 2024: New Fire Station Building coming right along: interior walls have been framed, electrical is being installed and plumbing inspections are complete. The Furnishing Commitee will be established to plan and pick out all furnishings.
February 20, 2024
Fire Building Update- The Drywall is receiving its third coat of joint compound, sanding will follow. The apparatus bay finish wall surfaces have been installed. The elevator was delivered this morning and installation will begin later this week or early next week. Interior doors frames arrive next week, and interior painting is scheduled to begin the 1st week of March. The project is still on schedule and will be completed in early May.
2/27/2024
Fire Station at Sunset
Photo: compliments of Great Falls Construction
3/13/2024 Update - Drywall installation was completed, and sanding and preparation continues for painting to begin next week. The computers, security and sound system work will continue this week. The mezzanine stair and balcony railing installation began today. The elevator installation began last week, and HVAC equipment is being installed. All projects are on schedule.
Susan Collins- 12/22/2022 Letter
Hi Vinny, I just wanted to reach out and share that the omnibus funding package has passed the Senate. I have highlighted your project below. Please let me know if you have any questions about this very exciting news!
For Immediate Release |
Contact: Annie Clark/Christopher Knight |
December 22, 2022 | 202-224-2523 |
More Than $36 Million for Maine Public Safety Facilities and Equipment Secured by Senator Collins
Washington, D.C.--U.S. Senator Susan Collins, a senior member of the powerful Senate Appropriations Committee, announced that she secured a total of $36,006,000 for public safety facilities and equipment in 27 Maine communities in the Fiscal Year 2023 appropriations bills.
The omnibus funding package passed the Senate by a vote of 68-29. It will now be passed by the House before heading to the President’s desk to be signed into law.
“Ensuring that Maine’s finest and bravest have modern facilities and equipment is essential to the delivery of efficient emergency services,” said Senator Collins. “This funding will replace aging public safety buildings and municipal complexes that are at risk of structural failure and not well suited to house modern equipment. In addition, it will allow communities to upgrade their equipment to better protect first responders and the public. I heard from local officials about how these projects will enhance the wellbeing of Mainers and improve the delivery of public safety services across the state.”
“On behalf of the citizens of Limerick and the Limerick Fire-Rescue Department I want to express our sincere gratitude to Senator Susan Collins,” said Vincent R. Pelletier Fire Chief of the Town of Limerick. “The Congressional support of our project to build a new fire and EMS station in Limerick will ensure the members of our community will continue to receive fire protection and emergency medical services well into the future. The new facility will have wide spread benefits to both Limerick and surrounding communities as we meet the future challenges of providing fire and EMS services to rural western Maine.”
Limerick Fire Station
Recipient: Town of Limerick
Project Location: Limerick, ME
Amount: $1,800,000
Project Purpose: To build a new fire station to serve Limerick and several smaller communities, including Cornish and Limington.